Management theorist W. Edwards Deming famously said, “In God we trust. All others must bring data.” I created this database to provide reliable data on the rejections or restrictions of battery, solar, and wind projects that have occurred around the world over the past two decades. If you are aware of a rejection or restriction that's not in the database, please click the Contribute button and complete the form. Please include a working URL to the relevant article or government entity so I can verify the information. If it checks out, I will add it to the database. Thanks.

Total Recorded Rejections

1108

Wind Rejections

587

Solar Rejections

449

Battery Rejections

72

NotesSource
12/18/2019USCABoard of SupervisorsHumboldt Countywind

The Humboldt County Board of Supervisors on Tuesday voted 4-1 to deny the Terra-Gen wind energy project, rejecting a widely controversial plan to build wind turbines on the Bear River and Monument ridges above Scotia.

Link
12/12/2019USNEBoard of CommissionersHamilton Countywind

By a unanimous vote Monday, the Hamilton County Board of Commissioners rejected a plan for a wind power generation facility in the county.

Link
12/12/2019USIABoard of SupervisorsHardin Countywind

Hardin County supervisors unanimously passed an indefinite moratorium on wind turbine building permits at its meeting Wednesday. In a 3-0 vote, supervisors passed a resolution placing a moratorium "effective immediately and indefinitely," on wind turbine permits.

Link
12/11/2019USNYTown boardSanfordwind

In a Town of Sanford board meeting, new restrictions were introduced to limit the distance turbines can be placed from personal property, and noise frequencies. Those restrictions passed, giving residents a new hope for the future.

Link
12/6/2019USMITown boardSherwood Townshipwind

The Sherwood Township Board voted 3-0 Thursday night in favor of an ordinance which was being backed by a local citizens group that is against to the siting of wind turbines in northwest Branch County….the ordinance establishes the maximum height of an industrial turbine at 330 feet. It also requires a setback from a non-participating parcel be 500 percent of the height of the tower and the required setback from a body of water is half a mile.

Link
11/24/2019USMIZoning Board of AppealsTuscola Countywind

A $10 million cash settlement meant to end litigation between alternative energy corporation NextEra Energy Resources and Tuscola County was not accepted by a pair of county entities this week. On July 25, the Tuscola County Airport Zoning Board of Appeals denied variances on 33 wind turbines associated with NextEra’s Pegasus Wind Project, which would place about 60 turbines in Juniata, Fairgrove and Gilford townships. The 33 turbines in question would be close enough to the Tuscola Area Airport that a variance must be obtained in order to continue construction.

Link
11/22/2019USNYBoard of HealthChautauqua Countywind

County "health officials will recommend that all cities, towns and villages within the county pass a proper wind law that restricts industrial wind towers, or IWTs, from being constructed within a mile and a half of any residence and generate 35 or fewer decibels in sound frequency."

Link
11/21/2019USCAPlanning CommissionHumboldt Countywind

The Terra-Gen wind energy project received a denial from the Humboldt County Planning Commission on Thursday, concluding an emotional series of meetings in which the commission appeared to be veering toward approval before swinging the other way.

Link
11/20/2019USIABoard of SupervisorsAdair Countywind

The amendment caps the number of commercial wind turbines or wind farms erected within the boundaries of Adair County at a total of no more than 535. Adair County currently has 532 turbines completed or under construction.

Link
11/9/2019USINBoard of Zoning AppealsHenry Countywind

The Henry County courtroom filled with cheers and applause Thursday evening after the Board of Zoning Appeals voted down an appeal from Big Blue River Wind Farm LLC.